Compulsory Acquisition of Land in Kenya: Process, Compensation and Appeals

By Christopher N. Rosana

A GNLegal editorial illustration of a public infrastructure corridor progressing through a carefully governed land-acquisition process.

Compulsory acquisition is not a sale negotiated between a willing buyer and seller. It is the State’s statutory power to acquire a title or other interest in land for a public purpose, subject to the constitutional safeguards in Article 40 and the process in Part VIII of the Land Act, 2012. The process may affect a whole parcel or only part of one, and it can affect more than the registered proprietor: a chargee, lessee, co-owner, occupier or spouse may each have an interest that needs to be identified.

That is why a notice should be treated as the start of an evidence-led process, not simply as an instruction to hand over title. The affected person needs to establish what land and interest are proposed for acquisition, why the public body says it is needed, which stage has been reached and which documents support the claim. The acquiring authority and the National Land Commission must likewise follow the statutory sequence rather than treating a project timetable as a substitute for it.

The constitutional threshold comes before the acquisition steps

Article 40(3) of the Constitution permits compulsory acquisition only where it is for a public purpose or in the public interest, is carried out under an Act of Parliament, and is accompanied by prompt payment in full of just compensation to the person affected. The constitutional protection also preserves a right of access to a court of law. The Land Act supplies the operational route; it does not turn every proposed project into a sufficient justification without the statutory conditions being met.

Under section 107, where national or county government considers particular land may be required, the relevant Cabinet Secretary or County Executive Committee Member must request the Commission to acquire it on its behalf. The Commission may reject a request that does not meet its prescribed criteria and guidelines or Article 40(3), and must inform the acquiring authority of a rejection within fourteen days. If the request passes that stage, the Commission maps and values the affected land and establishes whether the acquiring authority has identified and kept a register of people in actual occupation, including the duration of occupation and improvements.

The statutory definition of public purposes includes projects such as transport, public buildings, utilities, parks, security and defence installations, settlement of specified groups and analogous purposes. The stated purpose still matters in the particular case. Affected people should retain the notice and ask for clarity about the project, parcel reference, approximate area and proposed acquisition of the whole or only part of their interest.

Notice protects the register position and starts the factual record

Once a request is approved, section 107 requires the Commission to publish notice in the Gazette and county Gazette and deliver a copy to the Registrar and everyone who appears to be interested in the land. The notice must state the purpose, location, general description and approximate area. The Registrar must restrict or prohibit dealings with the affected portion until it vests in the acquiring authority, and make an entry of the intended acquisition in the register. Those steps can materially affect a pending sale, charge, subdivision or other dealing.

The Act defines interested persons broadly for this process. It includes people whose interests appear in the registry, their spouses, people actually occupying the land and spouses of those occupiers. A title holder should therefore not assume that only the name on the register is relevant, and an occupier should not assume that lack of registered title makes the notice irrelevant. The Commission’s file, official search, occupation evidence, lease, charge, succession documents and proof of improvements may each be important at later stages.

Notice also enables inspection. The Commission may give written authority to enter land named in a section 107 notice to assess its suitability. Entry into a dwelling, enclosed court or garden attached to a home requires the occupier’s consent or at least seven days’ written notice. Damage caused by inspection must be promptly compensated in full under section 109. Inspection is not the same as taking possession; keeping those stages separate helps prevent an early site visit from being mistaken for a completed acquisition.

The inquiry is where interests and claims must be put forward

At least thirty days after publication of the notice of intention, section 112 requires the Commission to appoint an inquiry to hear questions of propriety and claims for compensation. Notice of the inquiry must be published in the Gazette or county Gazette at least fifteen days beforehand and served on each apparent or claiming interested person. The notice calls on interested people to deliver their written compensation claims by the inquiry date.

The inquiry is the practical opportunity to put evidence before the Commission. An affected person should bring or submit the title and official search, identity and authority evidence, leases, charge documents, succession records, plans, photographs, approvals, receipts and valuation material relevant to the interest or improvements claimed. A claimant whose land is only partly taken should identify the portion carefully and explain any real effect on access, layout, use, earnings or the remaining land with plans or professional evidence where appropriate.

The Commission may summon and examine witnesses, administer oaths and require production of title documents. Both the public body for which the land is being acquired and every interested person may be heard, produce evidence and call or question witnesses. Participation should be focused: it is more useful to show a missing interest, incorrect boundary, unrecorded improvement or supported valuation issue than to make a general objection without documents. A person who cannot attend should act promptly on the notice rather than wait for an award to discover that key evidence was absent.

The award, payment and possession stages have separate consequences

After the inquiry, section 113 requires a written, separate award of compensation for every person whose interest the Commission has determined. The award conclusively records the acquired area, the Commission’s assessed value and the compensation form, while remaining subject to the Act’s review mechanisms. Section 114 requires notice of the award and offer of compensation to be served on every person found to be interested. Read it carefully: it should be matched against the parcel, area, interest, valuation material and any co-owner, lender, tenant or occupier whose interest was put forward.

Section 111 requires just compensation to be paid promptly in full to persons whose interests have been determined, and requires the acquiring authority to deposit compensation funds, survey and registration fees and other costs before acquisition. The Act allows several lawful forms, including an equivalent alternative parcel, money in a lump sum or instalments of no more than one year, a government bond, development rights, equity shares in a government-owned entity or another lawful form. Subject to the statutory framework, the owner elects the form of compensation. If the acquisition is not completed within twenty-four months after publication of the notice of intention, it lapses.

Payment can be complicated where no competent recipient is available, a recipient does not consent to the amount, or entitlement or shares are disputed. Section 115 deals with those situations; they are not reasons to ignore the award or abandon evidence of the interest. Section 119 also requires due diligence before payment, including final survey and determination of acreage, boundaries, ownership and value. If part of a title is acquired, a final survey and new title documents for affected parcels are required under section 118.

Possession is a later legal step. After an award, section 120 permits the Commission to take possession by serving each interested person with notice of the day when possession and title will vest in the national or county government. The taking of possession must not render people homeless. In urgent cases, the Act allows an accelerated route after fifteen days from publication of the intention notice, even before an award, but does not remove the need to serve the required possession and vesting notices. When possession is taken, the registered proprietor and Registrar must also be served.

Review and appeal must follow the current statutory route

Disagreement with a project, an acquisition process or an award does not by itself identify the remedy. The affected person should first secure the complete record: the acquisition request and notice, Gazette material, proof of service, official searches, inquiry notice, submissions, evidence, award, offer, possession notice and relevant valuation or survey material. That record is what shows whether the issue concerns the public-purpose basis, identification of the land, notice, participation, valuation, compensation, possession or the recognition of a particular interest.

For compulsory-acquisition matters, Part VIIIA of the Land Act establishes the Land Acquisition Tribunal. Under section 133C, a dissatisfied person may apply to it in the prescribed manner within thirty days of the Commission’s decision, and compulsory-acquisition matters must in the first instance be referred there despite sections 127 and 128. The Tribunal may confirm, vary or quash the Commission’s decision and can extend time for sufficient cause. A party dissatisfied with the Tribunal’s decision may appeal to court on the legal and procedural grounds stated in section 133D. The detailed challenge strategy belongs in the next guide; the immediate point is to identify the decision and preserve the deadline.

Compulsory acquisition is therefore a sequence of connected but distinct decisions. A person affected should not treat an early notice as the compensation award, a valuation as payment, or an inspection as possession. Keeping the statutory stages and evidence separate makes it easier to participate meaningfully, protect a registered or unregistered interest, and choose the right response before the transaction reaches vesting.

Service evidence belongs in the same file. Section 131 permits service personally, by registered post to the last known address and, where the address cannot after reasonable inquiry be found, through the occupier or a prominent part of the land. Different methods apply to a body corporate, and the Commission may also advertise in two nationally circulating newspapers in the stated circumstances. A person disputing notice should preserve the envelope, register entry, photographs and correspondence; an authority relying on notice should preserve its service record. The question is not merely whether someone eventually learned of the project, but whether the statutory record supports the step taken.

The process also has continuing public-purpose safeguards. Section 110 requires written certification that the land is required for a public purpose or public interest connected to the stated purpose. If the purpose or interest later fails or ceases, the Commission may offer the original owner or successor a pre-emptive right to re-acquire the land on returning the full compensation paid. That possibility is not an immediate remedy for every change in a project, but it illustrates why the purpose, scope and record of an acquisition should remain clear from the first notice through vesting.

Primary sources: Constitution of Kenya, Article 40; Land Act, 2012, sections 107–120 and 133A–133D.